Release Process
Overview
Summary of the RAPIDS release process for major and minor releases.
Intended audience
Project Leads
Operations
See also
Git branching model
RAPIDS uses a custom git branching model, adapted from git-flow to leverage the tools GitHub provides and also focus on release-driven development. From more details see our guide for our git branching methodology.
Migrating projects
For RAPIDS projects that are using another branching/development model, continue to develop with that approach until the next minor release. Given the version M.A.0
(where M
is the major version and A
is the minor version), create a development branch branch-M.B
where B=A+1
from the main
branch that has the latest minor release.
From this point forward you can follow the git branching & release model used by the RAPIDS team.
Major and minor releases
Both major and minor releases follow the same steps with little variation. For both, release types there are two key dates that need to be known well in advance:
Burn down date
Code freeze date
Release date
The burn down date
will always be several days before the code freeze date
which in turn is several days before the release date
. This is to ensure there is enough time to finish active development, and to handle any unknown bugs/issues.
Hotfixes
Hotfixes have their own process and are described here.
Burn down
Burn down is the process of locking down all issues slated for the release and moving issues not in this release to the following release. Additionally, all pending pull requests should be reviewed and aim to be merged before the code freeze date.
Timing
For the selection of a burn down date
, the general guidelines should be followed:
- Choose a
burn down date
at least 3 business days before acode freeze date
- Consult project leads to ensure key features will make the release with the anticipated date
- Communicate the decided
burn down date
to the development team immediately to ensure they can meet the deadline
Burn down ends at 11:59 PM PT on the final day of the process.
Process
NOTE: The processes below use the current release of M.A
, the next release of M.B
and future release M.C
(where B=A+1
, C=B+1
) for examples.
Project Leads
- Beginning of the
burn down date
remind development team to stop accepting new issues for theM.B
release (unless they are critical bugs/issues) - Work to merge existing pull requests targeting
M.B
- Move any pull requests or issues that are no longer a part of the
M.B
release to theM.C
project board or backlog (for backlog remove the issue from the project board)
Operations
- Beginning of the
burn down date
announce the burn down ofbranch-M.B
- Fork
branch-M.B
intobranch-M.C
for the new development branch - Create release
M.C
project board - Notify project leads process is complete
Also see the Burn down guide
Code freeze
Code freeze is the process when the release undergoes thorough testing. Pull requests are no longer accepted into the development branch. An exception may be made for hotfix issues. All pull requests from Burn Down should be merged before Code Freeze begins or be moved to the next release.
Timing
For the selection of a code freeze date
, the general guidelines should be followed:
- Choose a
code freeze date
at least 3 business days before therelease date
- Communicate the decided
code freeze date
to the development team immediately to ensure they can meet the deadline
Code freeze begins at 12:00AM PT the day immediately after Burn Down ends.
For example, if Burn down runs from Wednesday Feb 3rd until Tuesday Feb 9th, then Burn down ends at 11:59PM PT on Feb 9th and Code Freeze begins 12:00AM PT Feb 10th.
Process
NOTE: The processes below use the current release of M.A
, the next release of M.B
and future release M.C
(where B=A+1
, C=B+1
) for examples.
Generally the process for Code Freeze occurs around 10:00AM PT on the first day of Code Freeze.
Project Leads
- Move any open pull requests targeting
branch-M.B
to targetbranch-M.C
instead - Wait for confirmation from operations on the branch switch
- Continue
M.C
development - Respond promptly to operations if any issues are found with the
M.B
release
Operations
- Beginning of the
code freeze date
announce the code freeze ofbranch-M.B
- Switch GitHub default branch of project to
branch-M.C
- Create
M.B
release tracking project board - Notify project leads process is complete
Releasing
Timing
For the selection of a release date
, the general guidelines should be followed:
- Choose a
release date
at least 3-4 weeks from the previousrelease date
- Consult project leads to ensure key features will make the release with the anticipated date
- Communicate the decided
release date
to the development team immediately to ensure they can meet the deadline
Process
NOTE: The processes below use the current release of M.A
, the next release of M.B
and future release M.C
(where B=A+1
, C=B+1
) for examples.
Project Leads
- Beginning of the
release date
work with developers to close all outstanding issues and PRs - Assist operations team in testing and verifying documentation in release
M.B
PR - Review release
M.B
for approval - Help operations team in spot checking the deliverables post-release
Operations
- Beginning of the
release date
announce the release ofbranch-M.B
- Create release PR from
branch-M.B
that targetsmain
- Begin testing of conda, containers, and notebooks for correctness and functionality
- Work with development team to close outstanding PRs
- Review documentation to ensure version numbers and instructions are correct
- Enlist project reviewers to approve the release PR
- Merge release PR after approval
- Monitor process of automated tools
- Spot check deliverables to ensure correctness